Table A-1 – WBS for proposed project
ID Task Duration Resources 1 Analysis 6 d Rubab, Dua 2 Requirement Meetings 2 d Rubab, Dua 3 Communication with Stakeholders 2 d Rubab
4 Document Current System 21d Dua 5 Analysis Finished 1 d Rubab
6 Design 18 d Rubab, Dua
7 Design Database 5 d Rubab
8 Software Design 6 d Dua 9 Interface Design 3 d Rubab
10 Create Design Specifications 7 d Dua 11 Design Finished 1 d Rubab, Dua 12 Development 42 d Rubab, Dua 13 Develop System Module 32 d Rubab, Dua 14 Integrate System Module 6 d Rubab, Dua 15 Perform Initial Testing 3 d Dua
16 Development Finished 1 d Rubab
17 Testing 17 d Rubab, Dua 18 Perform System Testing 8 d Rubab
19 Document Issues Found 6 d Dua 20 Correct Issues Found 3 d Rubab
21 Testing Finished 1 d Rubab, Dua 22 Implementation 15 d Rubab, Dua 23 On-Site Installation 1 d Rubab, Dua 24 Support Plan for the System 15 d Rubab, Dua 25 Completion 9 d Rubab, Dua
26 System Maintenance 9 d Rubab
27 Evaluation 9 d Dua..give this wbs in tree form, Table A-1 presents a Work Breakdown Structure (WBS) for a proposed project. It includes tasks with IDs, durations, and allocated resources